MSTE - Mathematics, Surveying and Transportation Engineering
Common name: Math

Algebra, Trigonometry, Statistics, Geometry, Calculus, Differential Equations, Engineering Mechanics, Engineering Economy, Surveying, Transportation Engineering

Problem
An engineering company prepares an estimate for a job. The cost of preparing the estimate is Php10,000. The amount of profit over and above the Php10,000 is Php25,000 if their estimate is accepted. The probability that their estimate will be accepted 0.7 and the probability that their estimate will not be accepted is 0.3. What is the expected profit?

A.   Php12,500 C.   Php14,500
B.   Php13,500 D.   Php10,500

 

Problem
A conveyor is dispersing sands which forms into a conical pile whose height is approximately 4/3 of its base radius. Determine how fast the volume of the conical sand is changing when the radius of the base is 3 feet, if the rate of change of the radius is 3 inches per minute.

A.   2π ft/min C.   3π ft/min
B.   4π ft/min D.   5π ft/min

 

Problem
A new kind of atom smasher is to be composed of two tangents and a circular arc which is concave toward the point of intersection of the two tangents. Each tangent and the arc of the circle is 1 mile long, what is the radius of the circle? Use 1 mile = 5280 ft.

A.   1437 ft. C.   1347 ft.
B.   1734 ft. D.   1374 ft.

 

Situation
If a chord is selected at random on a fixed circle what is the probability that its length exceeds the radius of the circle?

  1. Assume that the distance of the chord from the center of the circle is uniformly distributed.
    A.   0.5 C.   0.866
    B.   0.667 D.   0.75
  2. Assume that the midpoint of the chord is evenly distributed over the circle.
    A.   0.5 C.   0.866
    B.   0.667 D.   0.75
  3. Assume that the end points of the chord are uniformly distributed over the circumference of the circle.
    A.   0.5 C.   0.866
    B.   0.667 D.   0.75